The per unit system is one of the most powerful calculation methods in power system analysis, transforming complex multi-voltage networks into simplified normalized calculations. Whether you're analyzing fault currents, calculating transformer impedances, or designing three-phase power systems, mastering the per unit system is essential for accurate and efficient power system engineering.
This normalization technique eliminates the confusion of working with multiple voltage levels simultaneously and makes equipment comparisons straightforward. Instead of juggling 480V, 13.8kV, and 138kV in the same calculation, everything becomes dimensionless quantities near 1.0, dramatically simplifying analysis while maintaining accuracy.
Understanding the Per Unit System Fundamentals
What is the Per Unit System?
The per unit (pu) system expresses power system quantities as decimal fractions of defined base values rather than in their actual units. Any electrical quantity can be expressed in per unit by dividing its actual value by an appropriate base value:
Per Unit Value=Base ValueActual Value
Key Concept: All per unit values are dimensionless (no units), making calculations cleaner and errors easier to spot.
Why Power Engineers Use Per Unit System
Advantages of Per Unit Analysis:
Benefit
Practical Impact
Simplifies multi-voltage calculations
Analyze entire power grid as single system
Eliminates unit conversions
No confusion between kV and V, MW and kW
Equipment comparison
Compare generators and transformers directly
Error detection
Values far from 1.0 indicate problems
Computer simulation
Reduces numerical errors in iterative calculations
💡 Pro Tip: Always use line-to-line voltage (VL−L) for three-phase base voltage, not phase voltage. This maintains consistency with three-phase power equations.
Selecting Appropriate Base Values
Standard Practice:
Base Power (Sbase): Choose a round number like 10 MVA, 100 MVA, or equipment rating
Base Voltage (Vbase): Use nominal system voltage at each level (13.8 kV, 138 kV, etc.)
Example Selection:
For a 100 MVA, 13.8 kV system:
Sbase = 100 MVA
Vbase = 13.8 kV
Step-by-Step Per Unit Calculations
Example 1: Three-Phase Generator Analysis
Given System:
Generator: 50 MVA, 13.8 kV, Xd" = 15%
Operating at: 52 MVA, 14.2 kV
Find: Per unit power and voltage on generator's base
Step 1: Identify Equipment Base Values
Generator nameplate ratings become its base values:
Sbase(gen) = 50 MVA
Vbase(gen) = 13.8 kV
Step 2: Calculate Per Unit Values on Generator Base
Spu=50 MVA52 MVA=1.04 puVpu=13.8 kV14.2 kV=1.029 pu
Interpretation: Generator operates at 104% of rated power and 102.9% of rated voltage - both within acceptable limits (typically ±10%).
Example 2: Transformer Impedance Conversion
Problem: A transformer has 8% impedance on its own 25 MVA base. Convert to system base of 100 MVA.
Given:
Ztransformer = 0.08 pu on 25 MVA base
V same on both bases (voltage doesn't change across transformer)
Result: On the 100 MVA system base, transformer impedance is 0.32 pu (32%).
warning
⚠️ Important: Transformer percent impedance is always given on the transformer's own MVA rating. You must convert it to system base before using it in system-wide calculations.
Example 3: Complete System Analysis
System Description:
Generator: 100 MVA, 13.8 kV, X = 0.15 pu
Step-up Transformer: 100 MVA, 13.8/138 kV, X = 0.10 pu
The per unit system transforms complex power system calculations into manageable analysis by normalizing all quantities to dimensionless values near 1.0. Whether you're calculating fault currents, analyzing voltage drops, or designing protection schemes, this method provides clarity and accuracy across multi-voltage networks.
Key Takeaways:
Choose consistent base values (typically Sbase and Vbase)
Convert all equipment impedances to common system base
Base voltage changes at transformers, base power stays constant
All calculations in per unit, convert back to actual values for final results
Per unit values near 1.0 indicate normal operation
Mastering per unit calculations is essential for power system engineers working with transformers, generators, and transmission networks. Practice with progressively complex systems to build confidence and proficiency.
Ready to apply per unit analysis to real systems? Start with single-generator configurations, then progress to multi-transformer networks and finally complete power systems with multiple voltage levels.
Understanding how to calculate 3-phase power is essential for electrical engineers, technicians, and anyone working with industrial electrical systems. Whether you're sizing circuit breakers, selecti....
Circuit breaker sizing is one of the most critical aspects of electrical system design and installation. Proper breaker sizing protects your electrical circuits from dangerous overcurrents while ensu....
The confusion between grounding, earthing, and neutral causes more electrical mistakes than almost any other concept in electrical work. Even experienced electricians sometimes use these terms interc....